You work as a project manager at Interstellar Bank. Your project is so big and the stakes are so high that you\'re not sure if your organization should commit to it. You propose to conduct a feasibility study to examine the benefits of the project. Feasibility study has been approved and started. Which of the following options is incorrect about this project?

你在星际银行担任项目经理。你的项目很大,风险很高,以至于你不确定组织是否应该立项。你提议进行一项可行性研究去检查项目的收益。可行性研究已获得批准并开始。关于该项目,下列哪个选项是不正确的?


A. The initiation process occurs at the beginning of a project when the probability of successfully completing the project is high and staffing levels are low

启动过程发生在项目开始时,此时成功完成项目的概率很高,人员配备水平很低 

B. The initiation process confirms that the next project phase should begin. This process is low cost and high risk

启动过程确认下一个项目阶段应该开始。这个过程成本低、风险高

C. The initiation process is the process of approving the implementation of the project and authorizing the use of organizational resources to begin work

启动过程是指批准实施项目,并授权使用组织资源开始工作的过程

D. The initiation process confirms that the next project phase should begin. Stakeholders have the greatest impact on the project's product or service during this process

启动过程确认下一个项目阶段应该开始。在此过程中,干系人对项目的产品或服务的影响最大


答案:A

启动过程组的特点是成本低、人员配备水平低、成功完成项目的概率低、风险高及干系人对项目的产品或服务的特性影响最大。项目发起人负责确认项目或项目的下一个阶段是否应该开始并授权资源分配。